- new culvert for the driveway has been installed at the street.

- all the top soil has been removed from the areas where new construction will take place

- awaiting shut off from gas company - should be this week we expect.

- designated substances study has been completed - report due on July 23.

- site plan amendment is nearly complete.  Trusting this is concluded this week.

- full building permit is also nearing completion.

- transition to our new temporary location is in effect - Sunday worship began there on July 13 - that's Lydia Trull Public School just one kilometer north east of our location at 80 Avondale St.