The last two weeks have seen some progress. Here's the update.
- new culvert for the driveway has been installed at the street.
- all the top soil has been removed from the areas where new construction will take place
- awaiting shut off from gas company - should be this week we expect.
- designated substances study has been completed - report due on July 23.
- site plan amendment is nearly complete. Trusting this is concluded this week.
- full building permit is also nearing completion.
- transition to our new temporary location is in effect - Sunday worship began there on July 13 - that's Lydia Trull Public School just one kilometer north east of our location at 80 Avondale St.
- Service times are 10 a.m. on Sundays - please feel free to join us.
- Pictures to follow shortly.